|

Piles supporting the tower legs, shown at low tide. Note that some of the piles exhibit almost complete loss of section |
Rehabilitation of Steel "H" Piles With Advanced Pile Encapsulation Process
During an underwater
inspection of the bearing piles supporting electric power transmission towers
in Baltimore Harbor, it was discovered that most of the piles had badly
corroded from a point approximately one foot below the cap to a depth of four
to five feet.
The owner elected to
reinforce the piles in the corroded areas by bolting 1/2" thick bent plates
to the webs and flanges. A cross sectional view of the bent plate repair is
found at the end of this report. To arrest any further corrosion to the piles
or the bent plates, the repairs were encapsulated by the Advanced Pile
Encapsulation (A-P-E) Process.
PROJECT
DATA
Owner: Baltimore
Gas and Electric - Baltimore, MD
Contractor: Mid
Atlantic Diving Contractors - Ellicott
City, MD
Materials:
Steel
Plates: Dura Bond - Export,
PA
Encapsulation: Advanced Pile Encapsulation Process, Master
Builders, Inc. - Cleveland,
OH
After the translucent
FRP jackets were installed around the piles and bent plates, A-P-E Pile
Grout was pumped into the space between the steel members and the FRP
jacket. The grout was batched, mixed and pumped by the plural component method, as shown in the schematic blow. The reactive components of the grout
were pre-mixed with inert silica filler and pumped through separate hoses to
the final mixing chamber, where they were blended just prior to entering
the FRP jacket. This method greatly reduces the problems normally associated
with handling pre-mixed or "hot-potted" epoxy grouts in the field. Because the
materials in the mixers, hoppers, and hoses are not catalyzed, the equipment
can be cleaned with water, virtually eliminating the need for solvents and
their effects on the environment.
The grout was
introduced into the jacket from the bottom up, through strategically placed
injection ports. The progression of the grout was visually monitored through
the translucent jacket to insure that all the steel surfaces were completely
surrounded by the protective polymer grout.
Return to Inland Projects List
|